Burwood
 

Photos & Highlights

Installation of Ganesh Statue

  • Clouds overhead in the form of Shri Ganesha

New images of burwood Jan 14

  • Interiors Completed

Photos for January 9 to 15, 2006

  • Commenced...
    - Carpet laying
    - Curtain hanging
  • Air conditioning connected and running... very cool!
  • Mosaics and tile laying completed in ensuites & kitchen
  • New driveway completed for entrance
  • Landscaping & exterior painting near completion
  • Night work commences!

Photos for January 2 to 8, 2006

  • 30 to 40 yogis working daily at Burwood
  • Yogis from around Australia and New Zealand also helping
  • Collective invited to Burwood for first morning meditation since renovations started
  • Final clean-up of meditation room
  • Tiling commenced to entrance
  • Door/window frame installed for Sir CP's room
  • Painting of rear area
  • Mosaic tiles installed in ensuites
  • Further paving of rear Court yard and rear garden steps
  • Timber decking for rear bedroom

Photos for December 26 to Jan 1

  • Tiling of ensuites
  • Kitchen roof tiling
  • Paving of side Court yard
  • Painting of front verandah
  • Landscaping of rear garden
  • Sandstone flagging of front fence and main entrance
  • Pergola for front entrance
  • Boarder mosaics for kitchen floor

Photos for December 19 to 25, 2005

  • Wall and ceiling decorations started in Shri Mataji's bedroom
  • Work continues on wall and floor Mosaics for ensuites
  • Decorative ceiling cornice completed and painting commenced in Sadhana Didi's bedroom
  • Courtyard plinth stand for Ganesha statue commenced
  • Waterproofing completed for ensuites
  • Kitchen ceiling/flooring timber work commenced

Photos for December 12 to 18, 2005

  • Painting completed in Shri Mataji's bedroom
  • Painting completed to front of Burwood
  • Panel designs for ceiling and courtyard completed (see photos)
  • Carpet chosen and ordered
  • Sandstone flagging for front brick fence ordered
  • Design commences on Mosaic designs for ensuites and dining floor areas (see photos)
  • Waterproofing completed for ensuites
  • Steel beams fitted in place for kitchen
  • More kitchen 3D drawings - Artist's Impressions (see photos)

Photos for December 5 to 11, 2005

  • Woodwork in Shri Mataji's room completed... ready for painting
  • Fabrics for curtains and bedding selected
  • New covered area in side Court Yard commenced
  • Repairs to front of Burwood commenced
  • Installation of ducted air conditioning commenced
  • Kitchen slab poured
  • Brick work commenced on kitchen walls
  • Steel beam & columns prepared for kitchen room
  • View Kitchen 3D drawings - Artist's Impressions!

Photos for November 28 to Dec 4, 2005

  • Fabrics being selected for curtains and bedspread
  • Kitchen/dining area demolished and footings prepared for slab floor.
  • Garage demolished - area will be used as driveway for Shri Mataji's vehicle.
  • Wall & ceiling lining removed from old boy's dorm.
  • New roof added
  • Installation of ducted air conditioning commenced
  • Internal preparation commenced for painting
  • Kitchen appliances ordered

Photos for November 21 to 27, 2005

  • Wall removed in Shri Mataji's bedroom,
  • Building & design teams formed to coordinate national involvement
  • Ordered - Kitchen flooring, cupboards, appliances, external doors and windows.
  • Ensuites started and plumbing installed.
  • Landscaping commenced front area
  • Flooring ordered for ensuites, kitchen & rear yard

A photo essay of the rennovation of Burwood Ashram will be featured on this page in the coming weeks.

Note: Progress photos are located on a separate website that hosts photo albums (www.photobucket.com).

Click on a heading marked "Photos for... " to view photos for that week. You will be automatically directed to the 'photobucket.com' site where you can view the photos.

To return to this page, close the photobucket window.