→ Burwood Photos, June

Week of June 30
Work commences of internal stairs, roof gutters and downpipes. Work continues on roofing structure, internal rooms & bathroom plumbing.

 

Week of June 23
Work continues on roofing structure, internal rooms & bathroom plumbing

 

 

 

Week of June 16
Work continues on roofing structure, work commences on bathroom plumbing and hallway opening for internal stairs started.

 

Week of June 9
Wall frames in place. Work commenced on roofing and preparing for the rain!!

 

Week of June 1
Preparing wall frames for second floor bedrooms and bathrooms.